Mold Interfaces & InspectionChoose Components Against the Target Press

DME imperial and HASCO metric are component-system options, not automatic regional settings. Confirm locating, ejection, cooling, and electrical interfaces against the target press drawings and approved mold design. SPI classes below are reference classifications, not a tool-life warranty.

EXAMPLE COMPONENT SYSTEMDME / Imperial option

Specify required thread and coupler interfaces against the press and plant connections.

Locating Ring: Confirm locating and platen requirements against the target press drawing.
Ejectors: Confirm ejector components and dimensions against the approved mold design.
Sprue Bushing: Confirm nozzle and sprue interface against the press documentation.

Agree the required inspection method, report format, material certificates, and delivery records before the quotation is approved.

Discuss Press Interfaces
Metrology equipment for dimensional inspection
Quality VerificationInspection scope by agreement
Confirm equipment and reports per project

Define Tooling AcceptanceConfirm the Requirements in the Contract

If your project specifies an SPI class, share the applicable standard and edition. We can review it with the RFQ; scope, inspection, acceptance, and any tool-life commitment must be confirmed in the written agreement.

Production and tool life

State expected production quantity and the required tool-life target, with operating assumptions where known.

Steel and heat treatment

Specify required steel grades, heat treatment, and the material or process records to be supplied.

Mechanisms and components

List required slides, lifters, inserts, cooling, ejection, and press-interface components.

Trials and maintenance acceptance

Define trial samples, inspection criteria, maintenance scope, and the records needed for acceptance.

Mold Steel SelectionConfirm Material Against Project Requirements

General reference only. This table does not confirm Nodinson stock, certification, or the properties of material used on a project. Verify the selected grade and heat-treatment condition against the supplier's current documentation.

Steel grade

Origin: Confirm supplier and source
Select for part, resin, and production requirements
Hardness
Specify required condition
Surface Polishability

Set finish target and acceptance sample

Chemical Corrosion Resistance

Assess resin and operating environment

Project confirmation:

Confirm grade, heat treatment, and documentation against the approved project specification.

SPI Polish & VDI Spark TexturesReference Values for Specification Discussions

These are general finish references, not measured results or a guarantee for a particular mold. Confirm the applicable standard, texture source, and acceptance sample in the project specification.

Polished finishRa Define by specification

Polishing approach

Set the cosmetic target and review against an approved sample.

Textured finishRa Define by specification

Texture process

Specify texture source, area, and acceptance sample.

DME (Imperial) vs HASCO (Metric)Examples for Press-Drawing Review

DME / imperial and HASCO / metric are component-system options, not geographic defaults. The entries below are a requirements checklist; confirm exact parts and dimensions against the target press drawings, current supplier catalogs, and approved mold design.

Hardware ParameterNorth America (DME Imperial)Europe & Global (HASCO Metric)Production Risk / Mitigation
Locating and mountingDME
Specify required dimensions and components
HASCO
Specify required dimensions and components
Check against the target press and platen drawings.
Cooling connectionsDME
Specify thread and coupler requirements
HASCO
Specify thread and coupler requirements
Confirm compatibility with the plant's hoses and connections.
Ejection and guidanceDME
Specify pins and guide components
HASCO
Specify pins and guide components
Confirm replacement and maintenance requirements.
Lifting and clampingDME
Specify lifting and clamping interfaces
HASCO
Specify lifting and clamping interfaces
Review against approved handling and press requirements.
Electrical and hot runnerDME
Specify connectors, controller, and voltage
HASCO
Specify connectors, controller, and voltage
Confirm equipment compatibility before design approval.

Engineering Standards Takeaways (Quick Summary for Buyers & Audits)

1. Confirm press interfaces:Share the target press and platen drawings so interface requirements can be reviewed and included in the approved design.
2. Specify spare parts:List requested wear parts and quantities in the RFQ; confirm supply in the quotation.
3. Request material records:State the required steel grade and certificates or heat-treatment records in the RFQ, then confirm their scope before production.

Unsure which SPI class or regional fittings suit your press?

Email the target press details, preferred component system, production target, and inspection/report needs. Do not attach confidential CAD before a written NDA is in place.

Email Project Requirements